Thursday, November 11, 2010

Tiling completed, Painting Started (d89)

Today I got a called from my SS. He tentatively tells me that my PCI is due for the 21st of December. I'm not sure how confident he is with that date. The only thing I'm concerned with is the tiler who is only a one man crew, and he is slow. Great attention to detail though.

The program is, 19th Nov, Painting will be completed
Week starting the 22nd Nov, fit out will begin, electrical & plumbing
Tiler will be back on the 29th to complete the tiling. 3 weeks to finish (maybe possible)
I have organised my water-tank to be delivered on the 29th of Nov

I guess I have a countdown now. 42 Days to go

See the wrap on the front door.
Wrap on windows.

Driveway to go here.
What to do? Water tank plumbing
Gas hotwater system will go here.
Water tank here (due on the 29th, I had to organise this, not through Metricon)
Frnech doors
First coat of external paint to eaves
Closer look at door
Painted under here.

Telephone connection needed.

2 comments:

Robert Richmond said...

Did you get your water tank separately? We did ..Cost us around $3500 installed...

JayJay said...

Yes, we decided to get out water tank seperately. Ours cost a little more, cos it's extra slim, 800mm wide.